On July 28, 2026, we held a ceremonial kiln ignition event to mark the completion of the installation of a new kiln unit on one of the production lines of our Plant 5A, located in Mojokerto, East Java. The event, led by Chief Financial Officer Mr. Rudy Sujanto, was attended by the management personnel of Plant V, as well as guests consisting of representatives from the kiln unit’s supplier.
A significant investment made to replace the kiln was aimed at improving production efficiency, particularly in relation to energy cost, through the switch from a double-firing to a single-firing kiln. With it, we also recorded our fastest time for completing a project of this type – an installation completed in just 26 days.